Borik Residential Project.
Construction Status Update

We are pleased to share the latest construction update for the Borik Residential Complex, as the project continues to advance steadily toward completion.

Current Progress – 31. March 2025:

  • Reinforced Concrete Works: Structural works are actively underway on all buildings, progressing from the ground floor to the 1st floor.
  • Garage Construction: Reinforced concrete works are in progress beneath Buildings 4 and 5, strengthening the underground levels of the complex.
  • Electrical and Waterproofing Installations: These essential installations are being carried out continuously across the site, ensuring the long-term durability and comfort of each residential unit.

With each completed stage, Borik Residential Complex moves closer to becoming a modern, high-quality residential community, combining smart construction, premium design, and a prime coastal location in the heart of Zadar’s Borik district.