Borik Residential Project.
Construction Status Update

The development of the Borik Residential Complex is progressing steadily, bringing us closer to delivering a modern and high-quality residential environment in one of Zadar’s most desirable districts.

Key Construction Updates

🔹 75% of the Concrete Structure Completed
The reinforced concrete works have reached 75% completion, marking continued strong progress on the core structural elements across the complex.

🔹 Internal Water and Sewage Installations Underway
Installation of internal water and sewage systems is actively ongoing, ensuring the essential infrastructure is in place to support all future residential utilities.

🔹 Test Installation of Aluminium Window System
mock-up aluminium window has been successfully installed, allowing the team to fine-tune all crucial technical and visual details before full-scale production begins. This step ensures quality, precision, and consistency throughout the project.