Borik Residential Project.
Construction Status Update
We are pleased to report continued strong progress on the construction of the Borik Residential Complex, as we move closer to completing a modern and high-quality residential development in the heart of Zadar’s Borik district.
Key Construction Highlights – July 2025:
Concrete Structure Completed
The reinforced concrete works across all buildings are now fully completed, marking a major milestone in the construction process.
Dividing Walls Installation
The installation of internal dividing walls is progressing steadily, defining the layouts of individual apartments.
Water, Sewage & Electrical Installations
Work continues on water, sewage, and electrical installations throughout the complex, ensuring essential infrastructure is in place for all units.
Aluminium Windows Installation – Building 2
The installation of aluminium windows has begun in Building 2, contributing to energy efficiency and the modern architectural design of the complex.